KIRKA SOLID WASTE TRANSMISSION SYSTEM CONSTRUCTION WORK

Start Date: 30.05.2019

Client

Client Name

Finish Date: 12.07.2021

Eskişehir // Kırka

SF, USA

Share

Within the scope of the construction work, it was aimed to transfer the clay wastes from the factories belonging to ETİ Kırka Boron Operations Directorate to the new waste pond with the help of a conveyor belt and the following manufacturing was carried out for this purpose.

  • Manufacturing, assembly and commissioning of 2.5 km long conveyor belt

  • Completing all electrical and automation works and coupling them to the existing control system.

  • 3500 tons of Structural Steel Manufacturing

  • All Reinforced Concrete Fabrications